MSU: 3-Month Construction Look Ahead
As the weather begins to warm, attention is focused on projects to be constructed this coming year. Below is a listing of projects, both small and large, that will be bid within the next three months. Some of these projects have a well-established bid schedule, while projects further out may have tentative bid dates listed. For the latest information on upcoming projects for Missouri State University, please check our web site at: https://design.missouristate.edu/projects/construction-look-ahead.htm.
Shuttle Stop Canopy Refinishing, Bear Park North
Project Description: The shuttle stop canopy will be sandblasted to remove all of the existing paint to allow for the installation of a new paint finish. The areas to be painted include all of the metal components of the canopy except for the metal roof exterior, aluminum bench seats and directory cabinets. The shuttle stop will be in use during the refinishing process. The work will be divided into two phases allowing a portion to be occupied. An add alternate to the project will be to remove and replace all of the existing joint sealant at the concrete wall joints.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: $70,000
Issue for Bid: February 27, 2018
Bid Opening: March 13, 2018
Award of Contract: March 15, 2018
Start of Construction: June 4, 2018
MSU Branding, William H. Darr Agricultural Center
Project Description: The project includes adding the Missouri State University wordmark above the donor signage at the reception desk in Bond Learning Center. The wordmark will be metal letters with color and finish to match the existing donor letters. A new Bear Head logo will be mounted to Pinegar Arena above the existing building sign.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: $4,000
Issue for Bid: February 27, 2018
Bid Opening: March 13, 2018
Award of Contract: March 22, 2018
Start of Construction: Upon Award
Construction of NPHC Plots
Project Description: Missouri State University is interested in constructing a location known as NPHC Plots on our campus. This is a location that provides a presence on campus for historically African American fraternities and sororities. The site will be the patio to the east of McDonald Arena. Two pergolas will be erected, an accessible entrance added, and plaques will be mounted to the short wall surrounding the patio.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: $200,000
Issue for Bid: February 27, 2018
Bid Opening: March 13, 2018
Award of Contract: March 22, 2018
Start of Construction: April 30, 2018
Install Dressing Rooms, Plaster Student Union
Project Description: This project will include the addition of a two new dressings rooms within an existing store at Plaster Student Union. The existing carpet is to be removed with the concrete floors stained and polished.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: $12,000
Issue for Bid: March 13, 2018
Bid Opening: March 27, 2018
Award of Contract: April 3, 2018
Start of Construction: Upon Award
Repair Parking Garage, Kenneth E. Meyer Alumni Center
Project Description: This project will include structural repairs to the parking garage located at the Kenneth E. Meyer Alumni Center.
Consultant: Structural Engineering Associates
Estimated Construction Cost: $440,000
Issue for Bid: March 15, 2018
Bid Opening: March 29, 2018
Award of Contract: April 18, 2018
Start of Construction: Upon Award
FY18 Preventative Parking Lot Maintenance, Parking Lots
Project Description: This includes preventative parking lot maintenance for the Springfield Campus.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: TBD
Issue for Bid: March 22, 2018
Bid Opening: April 5, 2018
Award of Contract: April 18, 2018
Start of Construction: May 21, 2018
Exterior Envelope Improvements, Hill Hall
Project Description: This project will include an investigation of the exterior envelope at Hill Hall to ensure it is sound to prevent water damage to newly renovated interior spaces.
Consultant: Structural Engineering Associates
Estimated Construction Cost: $500,000
Issue for Bid: March 22, 2018
Bid Opening: April 5, 2018
Award of Contract: April 18, 2018
Start of Construction: Upon Award
Einstein Brothers Infill, Glass Hall
Project Description: This project will include architectural and mechanical work for an infill installation of Einstein Brothers at Glass Hall.
Consultant: Hood-Rich Architecture
Estimated Construction Cost: $275,000
Issue for Bid: March 22, 2018
Bid Opening: April 5, 2018
Award of Contract: April 18, 2018
Start of Construction: May 21, 2018
Renovate Room 115, Meyer Library
Project Description: This project will renovate Room 115 within the Meyer Library to include the removal of the north-side counter, carpet replacement, locker removal, and paint applications.
Consultant: MSU Planning, Design & Construction
Estimated Construction Cost: TBD
Issue for Bid: March 27, 2018
Bid Opening: April 10, 2018
Award of Contract: April 17, 2018
Start of Construction: May 19, 2018
Paint Rooms and Replace Carpet, Wells and Scholars House
Project Description: This project includes paint application to all student rooms and the replacement of carpet within the corridors of Wells and Scholars House.
Consultant: Studio V Design
Estimated Construction Cost: $150,000
Issue for Bid: April 3, 2018
Bid Opening: April 17, 2018
Award of Contract: May 17, 2018
Start of Construction: May 21, 2018
Replace Drapes, Woods House
Project Description: This project includes the replacement of drapes within the student rooms.
Consultant: Studio V Design
Estimated Construction Cost: $125,000
Issue for Bid: April 3, 2018
Bid Opening: April 17, 2018
Award of Contract: May 17, 2018
Start of Construction: May 21, 2018
Flooring Improvements, Kings Street Annex
Project Description: This project involves the replacement of an alternative floor covering at the Kings Street Annex.
Consultant: Hood-Rich
Estimated Construction Cost: TBD
Issue for Bid: April 12, 2018
Bid Opening: April 26, 2018
Award of Contract: May 17, 2018
Start of Construction: Upon Award
Correct Water Infiltration, Hammons House and Hutchens House
Project Description: This project will correct water infiltration issues on the north side of Hammons House and Hutchens House.
Consultant: Esterly, Schneider & Associates
Estimated Construction Cost: $110,000
Issue for Bid: May 10, 2018
Bid Opening: May 24, 2018
Award of Contract: May 31, 2018
Start of Construction: Upon Award
Replace Exterior Doors, The Monroe
Project Description: This project will consist of the replacement of all exterior doors and hardware for The Monroe and will provide necessary electrical to connect to the access control system.
Consultant: Esterly, Schneider, & Associates
Estimated Construction Cost: $20,000
Issue for Bid: May 10, 2018
Bid Opening: May 24, 2018
Award of Contract: May 31, 2018
Start of Construction: Upon Award
Replace Windows, Sunvilla Tower
Project Description: This project includes the replacement of specified windows within Sunvilla Tower.
Consultant: Esterly Schneider, & Associates
Estimated Construction Cost: $55,000
Issue for Bid: May 10, 2018
Bid Opening: May 24, 2018
Award of Contract: May 31, 2018
Start of Construction: Upon Award
This will be the last 3-month construction look ahead that I personally send out. After more than 27 years here at Missouri State University I have decided to move on and retire from MSU. If you would like to read a bit more about what has transpired here at Missouri State University these past 27 years, please check out our web site located here. It has been a great run. Together much has been accomplished. I hope that each of you, no matter what part you may have played in our projects over the past 27 years, are as proud of what you did as I am proud of what you did for Missouri State University.